How the projection works
A need is met when the balance on its date covers it; otherwise shortage = need − balance available
Same-day events: deliveries are counted before needs. Cancelled deliveries are left out.
Affected activities = the activities named on needs with a shortage
- Assumptions, shown with every result: a delivery arrives in full on its expected date and can be used that day; quantities are in the material's unit as entered; no wastage or rejection is allowed for (add it to the need if your site expects it).
- Partial deliveries are separate rows of the same material. A delivery's status (expected, partly delivered, delivered) is shown on the timeline; only cancelled changes the arithmetic.
- A need or delivery for a material not in the materials list, a missing date or a zero quantity is listed as a row to fix, not guessed.
Worked example (the sample project)
GreenField Turf Systems (sample) is to deliver 60 turf rolls for Site B's turf laying on 25 November 2026. The first truck brings 40 rolls on 20 November; the balance of 20 is promised for 2 December. On 25 November the projection is 20 rolls short and Site B's turf laying is held up; the balance closes the gap on 2 December. Infill sand, opened with 5 t and 30 t due on 22 November, covers the 30 t needed on 28 November.
Common questions
Is the result a stock figure?
No. It is a projection from the quantities and dates you enter: a delivery is assumed to arrive in full on its expected date and to be usable that day. Real stock is what was received and accepted at site.
How is a partial delivery entered?
As two deliveries of the same material: the part that arrived (or will arrive) on one date and the balance on its later date. The sample shows 40 of 60 rolls first and 20 later.
What does a shortage mean here?
On that required-by date the projected quantity is less than the activity needs. The activity named on that need is listed as affected.
Are cancelled deliveries counted?
No. Set the status to cancelled and the delivery is left out of the projection.
Is anything sent to Khanal Group?
No. The planner runs in your browser; a link with your table is made only when you choose Share with inputs.