K-Projects
Mark labour attendance and prepare wage sheets in K-Projects
The project's Labour tab keeps daily attendance of your own workers and contractors' gangs. A manager locks each day and prepares wage sheets from it.
Last updated
What you need
- The Project manager or Organisation admin role to register workers, lock days and prepare wages
- The Site engineer role on the project to mark attendance
- Each worker's trade, employer (own or a contractor), daily rate and OT rate
- Labour contractors added in Contractors & suppliers
Register workers and put them on the project
- Click Labour in the left menu.
- Open Add a worker and fill in the name, trade, skill, employer, daily rate and OT rate.
- Choose the project in Put on project and click Add worker.
- To add workers already in the register, open the project's Labour tab, then Workers, choose them under Put workers on this project and click Put on project.
Mark today's attendance
- Open the project and click the Labour tab.
- Click Mark today's attendance.
- To mark a whole gang at once, under Mark a whole gang choose the Gang / contractor, choose Mark all as Present, type the time in and out, and click Mark all.
- In the table, change the few who differ: Present, Half day or Absent, time in, time out and OT hours.
- Optional: tap Add GPS location.
- Click Save attendance.
- For a contractor who gives numbers only, fill Head counts (contractors reporting numbers) and click Add head count.
Lock the day (manager)
- Open the day's attendance and check it against the DPR note at the top.
- Click Lock sheet and confirm.
- To change a locked day, open Reopen this sheet, type the Reason and click Reopen.
Prepare and approve the wage sheet
- On the Labour tab, click Wage sheets.
- Choose the period From and To and click Prepare wage sheet.
- Add advances and deductions for each worker and save.
- Ask another manager to open the sheet and click Approve wage sheet.
- Print the muster roll and the register of wages from the approved sheet.
Good to know
- The page compares attendance with the DPR manpower of the same date and warns when the two differ.
- Attendance inside an approved wage period cannot change until that wage sheet is cancelled.
- Man-hours gives strength and man-hours by trade, contractor and day, with a CSV download. Labour plan and Productivity are on the same tab.
- Only the last 4 digits of Aadhaar are recorded for a worker.
Common errors
"No workers on this project yet. A manager puts workers on the project under Workers."
Ask a manager to put workers on the project from the register, then open attendance again.
"Attendance older than N days is entered by a manager."
The day is past the limit set for site engineers. Ask a project manager to enter it.
"This date is in the approved wage sheet of …: attendance cannot change until that wage sheet is cancelled."
The wages for that period are approved. A manager must cancel the wage sheet with a reason before attendance can change.
"Saved, except: …"
Some lines were not saved. The message lists them and why. Correct those lines and save again.
Still stuck?
Email hello@khanals.in with the app name, what you clicked and the exact message you saw. Do not send passwords, PINs or authenticator codes. You can also use the contact page.